ISCOM010-0802
Mod. DSR
User Manual
DSR DELAY ON STAR/DELTA
Read all instructions carefully
The multifunction time relay
DSR
is a device standardised in 1-module DIN container,
designed to operate in environments with normal pollution level.
It is designated to manage the three-phase motors start-up and permits, after a certain delay,
the passing from star to the delta confi guration.
SAFETY WARNINGS
During the installation and operation of the instrument, proceed in accordance with the
instructions below:
1) The instrument should be installed by a competent operator following the
installation diagrams carefully
2) The instrument should be installed in a panel from which no access can be gained to
the terminals after installation
3) Do not power or connect the instrument if any part of it is damaged
4) The electrical system of the building in which the instruments is to be installed
should have a switch and a protective device against over-currents
5) The instrument is designed for installations with over-voltage category III and
pollution level 2, in accordance with the EN 61010-1 standard.
TECHNICAL SPECIFICATIONS
Power supply: AC/DC 12 ÷ 240 V (AC 50÷60Hz) -15% ÷ +10%
Consumption: 0,7÷3 VA AC / 0,5÷1,7 W DC
Supply indication: green LED
Time range with potentiometer: t1: 0,1 s ÷ 100 days, t2: 0,1 s ÷ 1 s
Output
Number of contacts: 2 changeover
Output indication: red LED multifunction
Contact capacity: 16A 250V AC1 / 24V DC
Inrush current: 30A / < 3 s
Breaking capacity: 4000VA / AC1, 384W / DC
Mechanical life: 3x107
Electrical life: 0,7x105
Operating temperature: -20°C ÷ +55°C
Storage temperature: -30°C ÷ +70°C
Protection degree: IP40 from front panel
OPERATION
Operation conditions
While installing this device it is necessary to consider temperature rate of ambient devices
so the operation temperature stated in technical parameters is kept. It is necessary to
ensure air circulation so the operation temperature is not exceeded in any case.
It is necessary to avoid placing devices close to sources of electromagnetic disturbances to
ensure their correct function.
It is necessary to pay attention while connecting products to the circuit with appliances
that create electromagnetic disturbances (conductors, motors), or power cables close
to them. It is recommended to have the connection cables of a product (supply and
operating inputs) as short as possible and have them led separately into power conductors.
Handling and use
Use a screwdriver with an approximate width 2mm for installation and setting
Do not use brute force to screw input terminals (maximally 0,5 N/m).
Do not put exceeded pressure on to the holding parts of terminals so the inner
construction of the device is not damaged.
Protect the device against falls and excessive vibrations
Do not overload relay output contacts, mainly while using loads of another category
then AC1
If contacts of relay melted while switching big loads, it is necessary to use an inserted
contactor or power relay rated for required load in the current installation.
For a correct setting of the relay, observe the following operations:
setting the Rought time setting
t1
with its potentiometer (see time ranges in the box
“OPERATING DIAGRAMS”)
setting the Fine time setting with its potentiometer (between 10% and 100% of the
Rought time setting)
setting the delay time
t2
for the commutation from star to delta confi guration
(between 0,1 second and 1 second).
REFERENCE STANDARDS
Conformity to the EU directives:
2006/95/EC (Low Voltage)
89/336/EEC modifi ed by 92/31/EEC and 93/68/EEC (EMC)
is declared with reference to the following harmonised standards:
Safety:
EN 61010-1
Electromagnetic compatibility:
EN 61000-6-2, EN 61000-6-4
Dimensions
Wiring diagrams
Operating diagrams
Rough time
setting
t1
Fine time
setting t1
Time ranges
0,1-1 s
1-10 s
0,1-1 min
1-10 min
0,1-1 h
1-10 h
0,1-1 day
1-10 days
3-30 days
10-100 days
Fine time
setting
t2
Delay ON start / delta


Specyfikacje produktu

Marka: Vemer
Kategoria: Niesklasyfikowane
Model: DSR

Potrzebujesz pomocy?

Jeśli potrzebujesz pomocy z Vemer DSR, zadaj pytanie poniżej, a inni użytkownicy Ci odpowiedzą




Instrukcje Niesklasyfikowane Vemer

Vemer

Vemer PR-1DA Instrukcja

4 Października 2024
Vemer

Vemer TCR Instrukcja

3 Października 2024
Vemer

Vemer Set PC RF8 Instrukcja

1 Października 2024
Vemer

Vemer ADR-D Vision Instrukcja

22 Września 2024
Vemer

Vemer Athena.Temp Instrukcja

22 Września 2024
Vemer

Vemer FR NTC-4P3D Instrukcja

21 Września 2024
Vemer

Vemer HT NiPt-2P3A Instrukcja

21 Września 2024
Vemer

Vemer LSM-01 Instrukcja

18 Września 2024
Vemer

Vemer Phono Instrukcja

16 Września 2024

Instrukcje Niesklasyfikowane

Najnowsze instrukcje dla Niesklasyfikowane