Instrukcja obsługi Projecta BLT300


Przeczytaj poniżej 📖 instrukcję obsługi w języku polskim dla Projecta BLT300 (4 stron) w kategorii Ładowarka baterii. Ta instrukcja była pomocna dla 4 osób i została oceniona przez 2 użytkowników na średnio 4.5 gwiazdek

Strona 1/4
6/12/24 VOLT CARBON PILE
1000 AMP
LOAD TESTER
P/No. BLT300
CAUTION – BATTERIES PRODUCE EXPLOSIVE GASES, TO REDUCE THE RISK
OF EXPLOSION OR INJURY ALWAYS ENSURE:
No sparks or flames are present
Eye protection is worn
All vehicle or battery manufacturer’s instructions are followed
The load is “OFF” before connection or disconnection
Correct polarity, do not reverse connect
Beware of moving engine parts
NOTE
Carbon pile load testers produce a great amount of heat while the load is ‘ON’, do not apply the load for
more than 20 seconds at a time and allow time to cool between tests.
When operating the unit for the first time it is normal for a small amount of smoke to develop as the
lubricants used in the manufacturing process burn off.
SPECIFICATIONS
P/No. BTL300
Tests: Volts (0–24VDC)
6/12/24V Lead Acid Batteries
Battery Range: Up to 2000CCA (320Ah)
Test Load: Adjustable Carbon Pile
0–1000 AMPS
Maximum Load ‘ON’ Time: 20 seconds
Recommended Cool
Down Time: 2 minutes
Test time alert: Buzzer sounds after 15 sec
Cable length: 1400mm
Size: 350mm x 355mm x 175mm
Weight: 8.4kg
OPERATING INSTRUCTIONS
Battery Load Test
1. Connect the RED clamp to the Positive (+) battery terminal or post
2. Connect the BLACK clamp to the Negative (-) battery terminal or post.
Note: If testing a battery in the vehicle, ensure the engine and all loads are‘OFF’.
3. Check the battery’s open circuit voltage (OCV) on the DC Volt meter.
If the needle is in the green section of the ‘State of Charge’ scale (above 6.5V, 12.5V, 24.5V) the battery
has sufficient charge to test.
If the needle is in the red section (below 6.5V, 12.5V, 24.5V) the battery needs to be fully charged
before testing.
4. Determine the battery’s rated capacity in Cold Cranking Amps (CCA) or Amp hours (Ah) and calculate the
correct load current:
Cranking batteries with: Load current = 1/2 the CCA rating
Deep Cycle Batteries with: Load current = 3 x Ah rating
5. Turn the ‘Load Control Knob’ clockwise until the correct load current is reached on the DC Amps meter.
6. After 15 seconds the buzzer will sound to indicate the correct test time, immediately read the DC Volt
meter.
If the needle is in the green area of the ‘Battery Test’ scale the battery has passed the test.
If the needle is in the red area the battery has failed the test, quickly reduce the load current until the
needle moves back into the green area, and then read the approximate battery capacity in Ah or CCA
from the DC Amps meter.
ONCE THE METER HAS BEEN READ THE LOAD MUST BE TURNED OFF
IMMEDIATELY TO PREVENT OVERHEATING – TURN THE LOAD CONTROL
KNOB FULLY ANTI-CLOCKWISE.
Note: Battery ouput varies due to temperature change, the ‘Battery Test’ scale has four temperature
calibrations (21o, 10o, -1oand -18oCelcius). Use the closest scale to the approximate ambient temperature.


Specyfikacje produktu

Marka: Projecta
Kategoria: Ładowarka baterii
Model: BLT300

Potrzebujesz pomocy?

Jeśli potrzebujesz pomocy z Projecta BLT300, zadaj pytanie poniżej, a inni użytkownicy Ci odpowiedzą




Instrukcje Ładowarka baterii Projecta

Projecta

Projecta IC2500W Instrukcja

16 Września 2024
Projecta

Projecta BLT700 Instrukcja

13 Września 2024
Projecta

Projecta HDBC35 Instrukcja

5 Września 2024
Projecta

Projecta IC5000 Instrukcja

5 Września 2024
Projecta

Projecta HDBC20 Instrukcja

5 Września 2024
Projecta

Projecta HDBM4000 Instrukcja

5 Września 2024
Projecta

Projecta IC2500 Instrukcja

1 Września 2024
Projecta

Projecta PC2100 Instrukcja

1 Września 2024
Projecta

Projecta IC1500L Instrukcja

31 Sierpnia 2024
Projecta

Projecta IC1500 Instrukcja

29 Sierpnia 2024

Instrukcje Ładowarka baterii

Najnowsze instrukcje dla Ładowarka baterii